Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
89
Sanctioned (pure scheme)
₹56.94 L
Expenditure since inception
₹16.48 L
Balance cost (unspent)
₹40.47 L
Wage ₹20.76 L · Material ₹19.71 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
81 works
₹19.01 L sanctioned
₹11.00 L spent (58%)
02
Plantation
4 works
₹16.23 L sanctioned
₹2.00 L spent (12%)
03
Construction of Road and Culvert
1 works
₹15.00 L sanctioned
₹3.03 L spent (20%)
04
Construction of Well
2 works
₹5.29 L sanctioned
₹906 spent (0%)
05
Other Works
1 works
₹1.41 L sanctioned
₹42,478 spent (30%)
06
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
08
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
09
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)