Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
27
Sanctioned (pure scheme)
₹1.56 Cr
Expenditure since inception
₹96.97 L
Balance cost (unspent)
₹59.49 L
Wage ₹25.15 L · Material ₹34.35 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
13 works
₹49.98 L sanctioned
₹12.25 L spent (25%)
02
Construction of Embankment
1 works
₹47.29 L sanctioned
₹44.55 L spent (94%)
03
Constr of Cement Concrete Roads
1 works
₹29.49 L sanctioned
₹28.06 L spent (95%)
04
Construction of Well
5 works
₹11.24 L sanctioned
₹5.82 L spent (52%)
05
Construction of Bund
1 works
₹6.56 L sanctioned
₹16,785 spent (3%)
06
Constr of Aganwadi
1 works
₹5.80 L sanctioned
₹1.55 L spent (27%)
07
Solid and Liquid Waste Management
2 works
₹3.94 L sanctioned
₹3.51 L spent (89%)
08
Cattle Shed
1 works
₹1.02 L sanctioned
₹14,069 spent (14%)
09
Construction of NADEP/Vermi Compost Pit
1 works
₹90,995 sanctioned
₹71,809 spent (79%)
10
Rural Housing
1 works
₹23,490 sanctioned
₹22,059 spent (94%)