Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
32
Sanctioned (pure scheme)
₹81.58 L
Expenditure since inception
₹58.01 L
Balance cost (unspent)
₹23.57 L
Wage ₹11.44 L · Material ₹12.14 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
2 works
₹55.52 L sanctioned
₹41.79 L spent (75%)
02
Construction of Well
9 works
₹20.80 L sanctioned
₹12.18 L spent (59%)
03
Rural Housing
20 works
₹4.70 L sanctioned
₹4.01 L spent (85%)
04
Plantation
1 works
₹55,852 sanctioned
₹2,751 spent (5%)
05
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Fish Drying Infrastructure
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)