Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
39
Sanctioned (pure scheme)
₹2.01 Cr
Expenditure since inception
₹1.11 Cr
Balance cost (unspent)
₹89.26 L
Wage ₹45.44 L · Material ₹43.82 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
13 works
₹80.64 L sanctioned
₹26.98 L spent (33%)
02
Construction of Check Dam/Stop Dam
8 works
₹74.36 L sanctioned
₹47.73 L spent (64%)
03
Construction of Road and Culvert
1 works
₹24.46 L sanctioned
₹22.02 L spent (90%)
04
Construction of Tank
1 works
₹9.61 L sanctioned
₹7.21 L spent (75%)
05
Farm Pond
3 works
₹4.43 L sanctioned
₹4.24 L spent (96%)
06
Well Recharge
1 works
₹2.60 L sanctioned
₹61,356 spent (24%)
07
Rural Housing
10 works
₹2.33 L sanctioned
₹1.64 L spent (70%)
08
Cattle Shed
2 works
₹2.29 L sanctioned
₹1.02 L spent (45%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)