Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
20
Sanctioned (pure scheme)
₹55.72 L
Expenditure since inception
₹29.55 L
Balance cost (unspent)
₹26.17 L
Wage ₹15.23 L · Material ₹10.94 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
5 works
₹29.26 L sanctioned
₹12.59 L spent (43%)
02
Construction of Trench
3 works
₹23.64 L sanctioned
₹15.20 L spent (64%)
03
Rural Housing
12 works
₹2.82 L sanctioned
₹1.77 L spent (63%)
04
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)