Monitor — Ongoing Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Works ongoing
34
Sanctioned (pure scheme)
₹38.41 L
Expenditure since inception
₹9.78 L
Balance cost (unspent)
₹28.63 L
Wage ₹11.52 L · Material ₹17.11 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹20.00 L sanctioned
₹44,554 spent (2%)
02
Plantation
4 works
₹9.35 L sanctioned
₹2.31 L spent (25%)
03
Rural Housing
27 works
₹6.34 L sanctioned
₹4.72 L spent (74%)
04
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.79 L spent (100%)
05
Community Sanitary Complex
1 works
₹92,000 sanctioned
₹50,340 spent (55%)
06
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)