Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
44
Sanctioned (pure scheme)
₹90.71 L
Expenditure since inception
₹61.91 L
Balance cost (unspent)
₹28.80 L
Wage ₹16.25 L · Material ₹12.55 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹40.07 L sanctioned
₹30.52 L spent (76%)
02
Construction of Well
8 works
₹24.42 L sanctioned
₹13.85 L spent (57%)
03
Constr of GP Bhawan
1 works
₹10.00 L sanctioned
₹9.80 L spent (98%)
04
Rural Housing
31 works
₹7.28 L sanctioned
₹3.51 L spent (48%)
05
Farm Pond
2 works
₹7.09 L sanctioned
₹4.19 L spent (59%)
06
Plantation
1 works
₹1.84 L sanctioned
₹3,915 spent (2%)
07
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)