Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
26
Sanctioned (pure scheme)
₹61.59 L
Expenditure since inception
₹39.18 L
Balance cost (unspent)
₹22.41 L
Wage ₹10.35 L · Material ₹12.06 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹16.62 L sanctioned
₹16.33 L spent (98%)
02
Construction of Check Dam/Stop Dam
2 works
₹16.57 L sanctioned
₹14.23 L spent (86%)
03
Plantation
5 works
₹10.49 L sanctioned
₹1.51 L spent (14%)
04
Farm Pond
2 works
₹7.71 L sanctioned
₹3.11 L spent (40%)
05
Terracing
3 works
₹4.36 L sanctioned
₹3.10 L spent (71%)
06
Land Development
1 works
₹2.57 L sanctioned
₹42,840 spent (17%)
07
Cattle Shed
3 works
₹1.51 L sanctioned
₹4,440 spent (3%)
08
Rural Housing
4 works
₹99,180 sanctioned
₹37,936 spent (38%)
09
Construction of NADEP/Vermi Compost Pit
4 works
₹49,920 sanctioned
₹3,040 spent (6%)
10
Well Recharge
1 works
₹25,899 sanctioned
₹2,202 spent (9%)