Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
15
Sanctioned (pure scheme)
₹50.53 L
Expenditure since inception
₹26.85 L
Balance cost (unspent)
₹23.68 L
Wage ₹8.03 L · Material ₹15.65 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
3 works
₹10.90 L sanctioned
₹5.38 L spent (49%)
02
Construction of Check Dam/Stop Dam
3 works
₹10.55 L sanctioned
₹7.13 L spent (68%)
03
Constr of Food Grain storage
1 works
₹8.99 L sanctioned
₹2.96 L spent (33%)
04
Land Development
1 works
₹8.74 L sanctioned
₹7.79 L spent (89%)
05
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹73,644 spent (15%)
06
Well Recharge
1 works
₹3.36 L sanctioned
₹91,616 spent (27%)
07
Cattle Shed
2 works
₹2.49 L sanctioned
₹1.89 L spent (76%)
08
Construction of NADEP/Vermi Compost Pit
2 works
₹24,960 sanctioned
₹760 spent (3%)
09
Rural Housing
1 works
₹24,795 sanctioned
₹3,120 spent (13%)
10
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)