Monitor — Ongoing Works
Rollup last refreshed: 2026-10-14 07:05:44.899714
Works ongoing
13
Sanctioned (pure scheme)
₹60.77 L
Expenditure since inception
₹12.33 L
Balance cost (unspent)
₹48.44 L
Wage ₹16.71 L · Material ₹31.72 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- SHIVPURI — KOLARAS−₹34,632
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹43.71 L sanctioned
₹7.03 L spent (16%)
02
Plantation
6 works
₹9.85 L sanctioned
₹2.31 L spent (23%)
03
Construction of Well
2 works
₹4.00 L sanctioned
₹71,020 spent (18%)
04
Construction of Trench
3 works
₹3.20 L sanctioned
₹2.29 L spent (71%)
05
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)