Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 06:52:44.456709
Works ongoing
22
Sanctioned (pure scheme)
₹1.08 Cr
Expenditure since inception
₹1.38 L
Balance cost (unspent)
₹1.06 Cr
Wage ₹48.86 L · Material ₹57.34 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹58.46 L sanctioned
₹0 spent (0%)
02
Plantation
8 works
₹24.91 L sanctioned
₹1.09 L spent (4%)
03
Land Development
1 works
₹9.84 L sanctioned
₹0 spent (0%)
04
Construction of Bund
1 works
₹4.71 L sanctioned
₹0 spent (0%)
05
Construction of Well
1 works
₹3.87 L sanctioned
₹20,540 spent (5%)
06
Construction of Check Dam/Stop Dam
1 works
₹2.48 L sanctioned
₹0 spent (0%)
07
Rural Housing
7 works
₹2.00 L sanctioned
₹8,400 spent (4%)
08
Construction of Recharge Pits
2 works
₹1.31 L sanctioned
₹0 spent (0%)
09
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)