Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
56
Sanctioned (pure scheme)
₹83.79 L
Expenditure since inception
₹31.60 L
Balance cost (unspent)
₹52.19 L
Wage ₹15.14 L · Material ₹37.05 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹37.99 L sanctioned
₹3.59 L spent (9%)
02
Well Recharge
1 works
₹14.75 L sanctioned
₹11.03 L spent (75%)
03
Rural Housing
48 works
₹11.90 L sanctioned
₹9.44 L spent (79%)
04
Land Development
1 works
₹9.94 L sanctioned
₹5.99 L spent (60%)
05
Community Sanitary Complex
1 works
₹5.98 L sanctioned
₹40,730 spent (7%)
06
Plantation
2 works
₹1.91 L sanctioned
₹78,220 spent (41%)
07
Construction of NADEP/Vermi Compost Pit
2 works
₹1.32 L sanctioned
₹35,830 spent (27%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)