Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
21
Sanctioned (pure scheme)
₹47.23 L
Expenditure since inception
₹21.39 L
Balance cost (unspent)
₹25.84 L
Wage ₹9.48 L · Material ₹16.36 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
6 works
₹16.57 L sanctioned
₹4.55 L spent (27%)
02
Constr of GP Bhawan
1 works
₹10.00 L sanctioned
₹7.13 L spent (71%)
03
Construction of Check Dam/Stop Dam
3 works
₹6.00 L sanctioned
₹3.98 L spent (66%)
04
Farm Pond
3 works
₹5.78 L sanctioned
₹2.11 L spent (37%)
05
Construction of Well
2 works
₹4.60 L sanctioned
₹1.44 L spent (31%)
06
Constr of Gabion
1 works
₹1.90 L sanctioned
₹32,412 spent (17%)
07
Construction of Bund
1 works
₹1.39 L sanctioned
₹1.08 L spent (78%)
08
Rural Housing
4 works
₹99,180 sanctioned
₹76,455 spent (77%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)