MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-15 06:57:05.982177
to
Reset filters
Works ongoing
1,043
Sanctioned (pure scheme)
₹22.46 Cr
Expenditure since inception
₹11.98 Cr
Balance cost (unspent)
₹10.48 Cr
Wage ₹4.75 Cr · Material ₹5.72 Cr
Expenditure trend
₹62.01 Cr
This Week
₹36.72 Cr
Last Week
▲ 68.9% vs last week
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
  • VIDISHA — LATERI−₹52.78 L
Mandays trend
7,10,772
This Week
12,10,003
Last Week
▼ 41.3%
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
  • MORENA — MORENA0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
312 works
₹7.15 Cr sanctioned
₹2.60 Cr spent (36%)
02
Farm Pond
78 works
₹2.82 Cr sanctioned
₹1.81 Cr spent (64%)
03
Construction of Tank
6 works
₹2.60 Cr sanctioned
₹1.80 Cr spent (69%)
04
Construction of Check Dam/Stop Dam
66 works
₹2.59 Cr sanctioned
₹1.56 Cr spent (60%)
05
Construction of Well
74 works
₹2.23 Cr sanctioned
₹1.06 Cr spent (47%)
06
Rural Housing
404 works
₹1.18 Cr sanctioned
₹61.69 L spent (52%)
07
Construction of Road and Culvert
3 works
₹62.19 L sanctioned
₹53.54 L spent (86%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
4 works
₹56.54 L sanctioned
₹44.29 L spent (78%)
09
Constr of Gabion
21 works
₹53.86 L sanctioned
₹16.84 L spent (31%)
10
Construction of Trench
9 works
₹43.85 L sanctioned
₹22.84 L spent (52%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 404 1.18 0.62 0.56
53%
2 Plantation 312 7.15 2.60 4.55
36%
3 Farm Pond 78 2.82 1.81 1.01
64%
4 Construction of Well 74 2.23 1.06 1.17
47%
5 Construction of Check Dam/Stop Dam 66 2.59 1.56 1.04
60%
6 Constr of Gabion 21 0.54 0.17 0.37
31%
7 Construction of NADEP/Vermi Compost Pit 19 0.09 0.02 0.07
25%
8 Well Recharge 12 0.14 0.06 0.09
39%
9 Cattle Shed 9 0.08 0.04 0.04
51%
10 Construction of Trench 9 0.44 0.23 0.21
52%
11 Construction of Tank 6 2.60 1.80 0.80
69%
12 Solid and Liquid Waste Management 6 0.01 0.00 0.01
18%
13 Constr of Cement Concrete Roads 5 0.28 0.23 0.05
83%
14 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 4 0.57 0.44 0.12
78%
15 Constr of GP Bhawan 3 0.26 0.20 0.06
77%
16 Construction of Road and Culvert 3 0.62 0.54 0.09
86%
17 Land Development 2 0.29 0.19 0.10
67%
18 Other Works 2 0.02 0.01 0.02
27%
19 Repair & maint of Water Harvesting Structures 2 0.07 0.05 0.02
72%
20 Goat Shelter 1 0.01 0.00 0.00
26%
21 Culvert 1 0.13 0.12 0.01
89%
22 Terracing 1 0.02 0.01 0.01
59%
23 Repair & Maint of Community infrastructure 1 0.23 0.19 0.04
82%
24 Constr of Aganwadi 1 0.03 0.02 0.01
70%
25 Construction of Percolation Tank 1 0.05 0.01 0.03
30%
Total 1,043 22.46 11.98 10.48
All 25 rows (zero-value rows hidden) ⇩ Export to Excel