Monitor — Ongoing Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Works ongoing
12
Sanctioned (pure scheme)
₹1.53 Cr
Expenditure since inception
₹92.42 L
Balance cost (unspent)
₹60.63 L
Wage ₹46.17 L · Material ₹14.45 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹90.02 L sanctioned
₹64.07 L spent (71%)
02
Plantation
6 works
₹25.69 L sanctioned
₹5.98 L spent (23%)
03
Construction of Tank
1 works
₹23.48 L sanctioned
₹18.00 L spent (77%)
04
Construction of Well
2 works
₹8.91 L sanctioned
₹2.25 L spent (25%)
05
Piggery Shelter
1 works
₹2.99 L sanctioned
₹1.62 L spent (54%)
06
Construction of Recharge Pits
1 works
₹1.95 L sanctioned
₹50,142 spent (26%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)