Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
33
Sanctioned (pure scheme)
₹1.29 Cr
Expenditure since inception
₹62.59 L
Balance cost (unspent)
₹66.45 L
Wage ₹42.27 L · Material ₹24.17 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
3 works
₹71.81 L sanctioned
₹38.78 L spent (54%)
02
Construction of Well
7 works
₹26.97 L sanctioned
₹9.87 L spent (37%)
03
Farm Pond
3 works
₹13.53 L sanctioned
₹8.62 L spent (64%)
04
Plantation
3 works
₹7.41 L sanctioned
₹1.91 L spent (26%)
05
Construction of Recharge Pits
1 works
₹5.37 L sanctioned
₹1,320 spent (0%)
06
Rural Housing
16 works
₹3.95 L sanctioned
₹3.40 L spent (86%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)