Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
19
Sanctioned (pure scheme)
₹65.37 L
Expenditure since inception
₹39.16 L
Balance cost (unspent)
₹26.21 L
Wage ₹13.63 L · Material ₹12.58 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
7 works
₹15.04 L sanctioned
₹11.39 L spent (76%)
02
Construction of Percolation Tank
1 works
₹12.58 L sanctioned
₹11.67 L spent (93%)
03
Construction of Check Dam/Stop Dam
3 works
₹11.43 L sanctioned
₹3.85 L spent (34%)
04
Construction of Well
3 works
₹10.34 L sanctioned
₹7.36 L spent (71%)
05
Plantation
4 works
₹8.46 L sanctioned
₹4.84 L spent (57%)
06
Grass Land Development
1 works
₹7.51 L sanctioned
₹6,016 spent (1%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)