Monitor — Ongoing Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Works ongoing
11
Sanctioned (pure scheme)
₹28.59 L
Expenditure since inception
₹14.61 L
Balance cost (unspent)
₹13.98 L
Wage ₹11.50 L · Material ₹2.48 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹23.20 L sanctioned
₹12.04 L spent (52%)
02
Plantation
1 works
₹2.84 L sanctioned
₹97,610 spent (34%)
03
Rural Housing
8 works
₹1.98 L sanctioned
₹1.49 L spent (75%)
04
Constr of Cement Concrete Roads
1 works
₹57,150 sanctioned
₹10,020 spent (18%)
05
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Food Grain storage
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Canal
0 works
₹0 sanctioned
₹0 spent (0%)