Monitor — Ongoing Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Works ongoing
16
Sanctioned (pure scheme)
₹51.00 L
Expenditure since inception
₹17.59 L
Balance cost (unspent)
₹33.41 L
Wage ₹16.12 L · Material ₹17.29 L
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹22.12 L sanctioned
₹37,468 spent (2%)
02
Construction of Road and Culvert
1 works
₹13.25 L sanctioned
₹11.85 L spent (89%)
03
Plantation
2 works
₹10.12 L sanctioned
₹4.56 L spent (45%)
04
Construction of Well
1 works
₹3.28 L sanctioned
₹16,574 spent (5%)
05
Rural Housing
9 works
₹2.23 L sanctioned
₹63,788 spent (29%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)