Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
19
Sanctioned (pure scheme)
₹88.67 L
Expenditure since inception
₹23.47 L
Balance cost (unspent)
₹65.20 L
Wage ₹34.94 L · Material ₹30.26 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
12 works
₹32.43 L sanctioned
₹11.02 L spent (34%)
02
Construction of Road and Culvert
1 works
₹19.55 L sanctioned
₹4.76 L spent (24%)
03
Construction of Crematorium
1 works
₹9.83 L sanctioned
₹3.99 L spent (41%)
04
Constr of Gabion
1 works
₹9.05 L sanctioned
₹15,334 spent (2%)
05
Construction of Play field
1 works
₹8.36 L sanctioned
₹1.23 L spent (15%)
06
Construction of Tank
1 works
₹5.00 L sanctioned
₹80,821 spent (16%)
07
Farm Pond
1 works
₹3.35 L sanctioned
₹56,153 spent (17%)
08
Cattle Shed
1 works
₹1.10 L sanctioned
₹94,393 spent (86%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)