Monitor — Ongoing Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Works ongoing
7
Sanctioned (pure scheme)
₹13.81 L
Expenditure since inception
₹2.20 L
Balance cost (unspent)
₹11.61 L
Wage ₹5.44 L · Material ₹6.17 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
3 works
₹11.53 L sanctioned
₹1.53 L spent (13%)
02
Community Sanitary Complex
1 works
₹1.58 L sanctioned
₹45,288 spent (29%)
03
Rural Housing
3 works
₹70,470 sanctioned
₹21,642 spent (31%)
04
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)