Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Works ongoing
69
Sanctioned (pure scheme)
₹1.59 Cr
Expenditure since inception
₹93.85 L
Balance cost (unspent)
₹64.87 L
Wage ₹49.54 L · Material ₹15.33 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
2 works
₹49.89 L sanctioned
₹35.63 L spent (71%)
02
Construction of Check Dam/Stop Dam
3 works
₹43.69 L sanctioned
₹30.25 L spent (69%)
03
Construction of Tank
2 works
₹27.35 L sanctioned
₹16.13 L spent (59%)
04
Plantation
3 works
₹15.52 L sanctioned
₹2.16 L spent (14%)
05
Rural Housing
56 works
₹13.15 L sanctioned
₹8.49 L spent (65%)
06
Farm Pond
1 works
₹4.51 L sanctioned
₹77,540 spent (17%)
07
Construction of Trench
1 works
₹2.80 L sanctioned
₹39,559 spent (14%)
08
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹3,132 spent (2%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Land Development
0 works
₹0 sanctioned
₹0 spent (0%)