Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
31
Sanctioned (pure scheme)
₹30.03 L
Expenditure since inception
₹8.28 L
Balance cost (unspent)
₹21.75 L
Wage ₹13.19 L · Material ₹8.56 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
9 works
₹18.51 L sanctioned
₹5.23 L spent (28%)
02
Rural Housing
17 works
₹3.99 L sanctioned
₹48,573 spent (12%)
03
Construction of Well
1 works
₹3.22 L sanctioned
₹1.99 L spent (62%)
04
Works for Flood Control and Protection
1 works
₹1.81 L sanctioned
₹1,140 spent (1%)
05
Repair & maint of Pond/ Tank
1 works
₹1.33 L sanctioned
₹2,316 spent (2%)
06
Constr of Cement Concrete Roads
2 works
₹1.17 L sanctioned
₹54,030 spent (46%)
07
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)