Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
1,677
Sanctioned (pure scheme)
₹17.22 Cr
Expenditure since inception
₹6.06 Cr
Balance cost (unspent)
₹11.16 Cr
Wage ₹6.10 Cr · Material ₹5.07 Cr
Expenditure trend
₹33.04 L
This Week
₹56.93 Cr
Last Week
▼ 99.4% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹27.93 L
Mandays trend
-31,213
This Week
2,63,410
Last Week
▼ 111.8%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
223 works
₹5.65 Cr sanctioned
₹1.28 Cr spent (23%)
02
Rural Housing
1,216 works
₹2.86 Cr sanctioned
₹99.68 L spent (35%)
03
Construction of Well
86 works
₹2.58 Cr sanctioned
₹1.11 Cr spent (43%)
04
Construction of Road and Culvert
16 works
₹1.70 Cr sanctioned
₹97.23 L spent (57%)
05
Constr of Cement Concrete Roads
49 works
₹82.00 L sanctioned
₹36.56 L spent (45%)
06
Constr of Aganwadi
12 works
₹48.72 L sanctioned
₹16.59 L spent (34%)
07
Works for Flood Control and Protection
9 works
₹46.81 L sanctioned
₹20.92 L spent (45%)
08
Construction of Check Dam/Stop Dam
8 works
₹39.51 L sanctioned
₹2.31 L spent (6%)
09
Construction of Percolation Tank
10 works
₹35.78 L sanctioned
₹5.22 L spent (15%)
10
Construction of Tank
3 works
₹31.98 L sanctioned
₹11.35 L spent (35%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 1,216 2.86 1.00 1.86
35%
2 Plantation 223 5.65 1.28 4.36
23%
3 Construction of Well 86 2.58 1.11 1.46
43%
4 Constr of Cement Concrete Roads 49 0.82 0.37 0.45
45%
5 Construction of Road and Culvert 16 1.70 0.97 0.73
57%
6 Constr of Aganwadi 12 0.49 0.17 0.32
34%
7 Construction of Percolation Tank 10 0.36 0.05 0.31
15%
8 Works for Flood Control and Protection 9 0.47 0.21 0.26
45%
9 Construction of Check Dam/Stop Dam 8 0.40 0.02 0.37
6%
10 Construction of NADEP/Vermi Compost Pit 7 0.03 0.00 0.03
12%
11 Repair & maint of Pond/ Tank 5 0.10 0.01 0.09
6%
12 Construction of Toilets 4 0.02 0.01 0.01
66%
13 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 4 0.20 0.03 0.17
14%
14 Construction of Crematorium 3 0.06 0.01 0.05
15%
15 Community Sanitary Complex 3 0.03 0.01 0.02
41%
16 Constr of GP Bhawan 3 0.30 0.23 0.07
77%
17 Construction of Recharge Pits 3 0.11 0.02 0.09
19%
18 Construction of Tank 3 0.32 0.11 0.21
36%
19 Constr of Compound wall 3 0.14 0.11 0.03
81%
20 Constr of Kitchen Shed 2 0.00 0.00 0.00
46%
21 Construction of Trench 1 0.04 0.00 0.04
0%
22 Grass Land Development 1 0.08 0.00 0.07
5%
23 Cattle Shed 1 0.18 0.16 0.02
88%
24 Construction of Play field 1 0.03 0.02 0.01
80%
25 Terracing 1 0.02 0.02 0.01
67%
26 Farm Pond 1 0.03 0.00 0.03
1%
27 Well Recharge 1 0.06 0.00 0.05
5%
28 Repair & Maint of Community infrastructure 1 0.17 0.13 0.05
73%
Total 1,677 17.22 6.06 11.16
All 28 rows (zero-value rows hidden) ⇩ Export to Excel