Monitor — Ongoing Works

Rollup last refreshed: 2026-10-16 08:36:19.743515
to
Reset filters
Works ongoing
23
Sanctioned (pure scheme)
₹47.11 L
Expenditure since inception
₹31.27 L
Balance cost (unspent)
₹15.84 L
Wage ₹8.18 L · Material ₹7.67 L
Expenditure trend
−₹79.59 L
This Week
−₹78.03 L
Last Week
▼ 2% vs last week
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹37.79 L
Mandays trend
-34,721
This Week
-33,130
Last Week
▼ 4.8%
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹24.44 L sanctioned
₹22.65 L spent (93%)
02
Plantation
4 works
₹10.30 L sanctioned
₹1.53 L spent (15%)
03
Construction of Well
2 works
₹7.14 L sanctioned
₹4.36 L spent (61%)
04
Rural Housing
14 works
₹3.29 L sanctioned
₹1.58 L spent (48%)
05
Constr of Cement Concrete Roads
2 works
₹1.94 L sanctioned
₹1.14 L spent (59%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. Panchayat Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 KHANKHEDI 23 47.11 31.27 15.84
66%
Total 23 47.11 31.27 15.84
All 1 rows (zero-value rows hidden) ⇩ Export to Excel