MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
2,941
Sanctioned (pure scheme)
₹39.24 Cr
Expenditure since inception
₹20.17 Cr
Balance cost (unspent)
₹19.07 Cr
Wage ₹10.64 Cr · Material ₹8.42 Cr
Expenditure trend
₹56.93 Cr
This Week
₹182.70 Cr
Last Week
▼ 68.8% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
  • MORENA — JOURA−₹1.63 Cr
Mandays trend
2,63,410
This Week
21,46,699
Last Week
▼ 87.7%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,502

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
47 works
₹9.67 Cr sanctioned
₹6.93 Cr spent (72%)
02
Plantation
337 works
₹8.57 Cr sanctioned
₹2.40 Cr spent (28%)
03
Construction of Well
174 works
₹6.92 Cr sanctioned
₹3.89 Cr spent (56%)
04
Rural Housing
2,100 works
₹4.93 Cr sanctioned
₹2.21 Cr spent (45%)
05
Works for Flood Control and Protection
38 works
₹2.37 Cr sanctioned
₹1.23 Cr spent (52%)
06
Constr of Cement Concrete Roads
143 works
₹1.49 Cr sanctioned
₹1.07 Cr spent (72%)
07
Land Development
11 works
₹87.59 L sanctioned
₹46.20 L spent (53%)
08
Construction of Tank
7 works
₹87.14 L sanctioned
₹19.87 L spent (23%)
09
Cattle Shed
2 works
₹76.18 L sanctioned
₹69.88 L spent (92%)
10
Constr of Compound wall
6 works
₹58.51 L sanctioned
₹34.55 L spent (59%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 2,100 4.93 2.21 2.72
45%
2 Plantation 337 8.57 2.40 6.17
28%
3 Construction of Well 174 6.92 3.89 3.03
56%
4 Constr of Cement Concrete Roads 143 1.49 1.07 0.42
72%
5 Construction of Road and Culvert 47 9.67 6.93 2.74
72%
6 Works for Flood Control and Protection 38 2.37 1.23 1.14
52%
7 Construction of building/workshed for SHG 14 0.32 0.13 0.19
40%
8 Land Development 11 0.88 0.46 0.41
53%
9 Construction of Percolation Tank 10 0.34 0.07 0.28
20%
10 Community Sanitary Complex 10 0.04 0.04 0.01
80%
11 Solid and Liquid Waste Management 8 0.04 0.02 0.02
52%
12 Constr of Aganwadi 7 0.33 0.18 0.15
55%
13 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 7 0.53 0.08 0.45
15%
14 Construction of Tank 7 0.87 0.20 0.67
23%
15 Farm Pond 6 0.18 0.05 0.13
28%
16 Constr of Compound wall 6 0.59 0.35 0.24
59%
17 Repair & maint of Pond/ Tank 5 0.18 0.07 0.11
40%
18 Construction of Crematorium 5 0.12 0.04 0.08
36%
19 Cattle Shed 2 0.76 0.70 0.06
92%
20 Construction of Play field 2 0.07 0.05 0.03
63%
21 Construction of NADEP/Vermi Compost Pit 1 0.00 0.00 0.00
3%
22 Repair & Maint of Check Dam/Stop Dam 1 0.04 0.02 0.02
54%
Total 2,941 39.24 20.17 19.07
All 22 rows (zero-value rows hidden) ⇩ Export to Excel