Monitor — Ongoing Works
Rollup last refreshed: 2026-10-15 06:57:05.982177
Works ongoing
3
Sanctioned (pure scheme)
₹23.30 L
Expenditure since inception
₹14.55 L
Balance cost (unspent)
₹8.75 L
Wage ₹4.81 L · Material ₹3.94 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1 works
₹14.80 L sanctioned
₹10.58 L spent (71%)
02
Land Development
1 works
₹6.20 L sanctioned
₹2.32 L spent (37%)
03
Constr of GP Bhawan
1 works
₹2.30 L sanctioned
₹1.64 L spent (71%)
04
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of Aganwadi
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
08
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)