Monitor — Ongoing Works
Rollup last refreshed: 2026-10-15 06:57:05.982177
Works ongoing
17
Sanctioned (pure scheme)
₹32.23 L
Expenditure since inception
₹22.09 L
Balance cost (unspent)
₹10.14 L
Wage ₹1.89 L · Material ₹8.25 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
8 works
₹17.92 L sanctioned
₹12.07 L spent (67%)
02
Other Works
7 works
₹10.44 L sanctioned
₹7.45 L spent (71%)
03
Construction of Tank
1 works
₹3.60 L sanctioned
₹2.40 L spent (67%)
04
Rural Housing
1 works
₹27,000 sanctioned
₹16,704 spent (62%)
05
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)