Monitor — Ongoing Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Works ongoing
22
Sanctioned (pure scheme)
₹28.56 L
Expenditure since inception
₹7.76 L
Balance cost (unspent)
₹20.81 L
Wage ₹5.95 L · Material ₹14.86 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Aganwadi
1 works
₹14.91 L sanctioned
₹2.02 L spent (14%)
02
Rural Housing
14 works
₹3.99 L sanctioned
₹1.59 L spent (40%)
03
Plantation
2 works
₹3.91 L sanctioned
₹1.18 L spent (30%)
04
Construction of Tank
2 works
₹3.16 L sanctioned
₹1.03 L spent (33%)
05
Constr of Cement Concrete Roads
2 works
₹2.09 L sanctioned
₹1.93 L spent (92%)
06
Poultry Shelter
1 works
₹51,554 sanctioned
₹1,408 spent (3%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)