Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
210
Sanctioned (pure scheme)
₹58.43 L
Expenditure since inception
₹23.30 L
Balance cost (unspent)
₹35.13 L
Wage ₹32.03 L · Material ₹3.11 L
Expenditure trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Mandays trend
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
205 works
₹47.97 L sanctioned
₹19.85 L spent (41%)
02
Construction of Tank
1 works
₹3.38 L sanctioned
₹91,596 spent (27%)
03
Plantation
1 works
₹2.86 L sanctioned
₹63,248 spent (22%)
04
Construction of Well
1 works
₹2.60 L sanctioned
₹76,606 spent (29%)
05
Constr of GP Bhawan
1 works
₹1.36 L sanctioned
₹1.04 L spent (76%)
06
Well Recharge
1 works
₹25,899 sanctioned
₹10,440 spent (40%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)