| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Constr of Cement Concrete Roads | 6 | 5.31 | 2.16 | 3.15 | 41% |
| 2 | Plantation | 4 | 5.88 | 0.04 | 5.84 | 1% |
| 3 | Works for Flood Control and Protection | 4 | 15.81 | 7.63 | 8.18 | 48% |
| 4 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 2.17 | 0.27 | 1.90 | 13% |
| 5 | Rural Housing | 2 | 0.47 | 0.02 | 0.45 | 5% |
| 6 | Construction of Toilets | 1 | 0.69 | 0.60 | 0.09 | 87% |
| 7 | Farm Pond | 1 | 1.48 | 0.77 | 0.70 | 52% |
| 8 | Community Sanitary Complex | 1 | 0.69 | 0.43 | 0.26 | 62% |
| 9 | Constr of Food Grain storage | 1 | 0.16 | 0.00 | 0.16 | 0% |
| Total | 22 | 32.65 | 11.91 | 20.74 |