| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Works for Flood Control and Protection | 7 | 28.25 | 0.00 | 28.25 | 0% |
| 2 | Construction of Crematorium | 3 | 18.75 | 0.00 | 18.75 | 0% |
| 3 | Construction of Check Dam/Stop Dam | 3 | 18.70 | 0.00 | 18.70 | 0% |
| 4 | Construction of Tank | 2 | 67.43 | 0.00 | 67.43 | 0% |
| 5 | Plantation | 2 | 6.70 | 0.00 | 6.70 | 0% |
| 6 | Construction of Road and Culvert | 1 | 5.39 | 0.00 | 5.39 | 0% |
| 7 | Constr of GP Bhawan | 1 | 10.00 | 0.00 | 10.00 | 0% |
| 8 | Construction of Play field | 1 | 12.07 | 0.00 | 12.07 | 0% |
| 9 | Community Sanitary Complex | 1 | 0.43 | 0.00 | 0.43 | 0% |
| 10 | Repair & maint of Pond/ Tank | 1 | 9.98 | 0.00 | 9.98 | 0% |
| Total | 22 | 177.70 | 0.00 | 177.70 |