Monitor — Ongoing Works
Rollup last refreshed: 2026-08-05 08:30:05.836701
Works ongoing
11
Sanctioned (pure scheme)
₹1.30 Cr
Expenditure since inception
₹36.32 L
Balance cost (unspent)
₹93.35 L
Wage ₹30.81 L · Material ₹62.54 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
3 works
₹44.75 L sanctioned
₹25.65 L spent (57%)
02
Cattle Shed
1 works
₹37.85 L sanctioned
₹17,100 spent (0%)
03
Construction of Check Dam/Stop Dam
1 works
₹14.83 L sanctioned
₹1.34 L spent (9%)
04
Works for Flood Control and Protection
2 works
₹12.30 L sanctioned
₹1.35 L spent (11%)
05
Solid and Liquid Waste Management
1 works
₹11.99 L sanctioned
₹34,272 spent (3%)
06
Constr of GP Bhawan
1 works
₹5.79 L sanctioned
₹5.55 L spent (96%)
07
Construction of Play field
1 works
₹1.93 L sanctioned
₹1.80 L spent (93%)
08
Rural Housing
1 works
₹23,490 sanctioned
₹12,240 spent (52%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Constr of Aganwadi
0 works
₹0 sanctioned
₹0 spent (0%)