Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Works ongoing
22
Sanctioned (pure scheme)
₹97.61 L
Expenditure since inception
₹20.91 L
Balance cost (unspent)
₹76.70 L
Wage ₹55.88 L · Material ₹20.82 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
22 works
₹97.61 L sanctioned
₹20.91 L spent (21%)