Monitor — Ongoing Works
Rollup last refreshed: 2026-10-16 06:52:44.456709
Works ongoing
4,214
Sanctioned (pure scheme)
₹117.20 Cr
Expenditure since inception
₹1.18 Cr
Balance cost (unspent)
₹116.02 Cr
Wage ₹57.17 Cr · Material ₹58.84 Cr
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
120 works
₹26.04 Cr sanctioned
₹2.36 L spent (0%)
02
Cattle Shed
54 works
₹19.15 Cr sanctioned
₹51,300 spent (0%)
03
Plantation
695 works
₹15.66 Cr sanctioned
₹36.73 L spent (2%)
04
Construction of Check Dam/Stop Dam
128 works
₹7.49 Cr sanctioned
₹1.10 L spent (0%)
05
Construction of Tank
81 works
₹6.02 Cr sanctioned
₹1.37 L spent (0%)
06
Rural Housing
1,994 works
₹5.42 Cr sanctioned
₹66.73 L spent (12%)
07
Constr of GP Bhawan
90 works
₹4.39 Cr sanctioned
₹9,000 spent (0%)
08
Constr of Cement Concrete Roads
382 works
₹3.66 Cr sanctioned
₹3.64 L spent (1%)
09
Construction of Bund
40 works
₹3.50 Cr sanctioned
₹0 spent (0%)
10
Constr of Aganwadi
40 works
₹3.20 Cr sanctioned
₹1,800 spent (0%)