Monitor — Ongoing Works
Rollup last refreshed: 2026-10-10 07:05:33.857647
Works ongoing
4,250
Sanctioned (pure scheme)
₹117.29 Cr
Expenditure since inception
₹47.16 Cr
Balance cost (unspent)
₹70.13 Cr
Wage ₹36.35 Cr · Material ₹33.79 Cr
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
- KHARGONE — BHAGVANPURA-1,542
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
120 works
₹26.04 Cr sanctioned
₹9.05 Cr spent (35%)
02
Cattle Shed
54 works
₹19.15 Cr sanctioned
₹13.02 Cr spent (68%)
03
Plantation
695 works
₹15.66 Cr sanctioned
₹3.18 Cr spent (20%)
04
Construction of Check Dam/Stop Dam
128 works
₹7.49 Cr sanctioned
₹2.53 Cr spent (34%)
05
Construction of Tank
81 works
₹6.02 Cr sanctioned
₹1.01 Cr spent (17%)
06
Rural Housing
2,031 works
₹5.52 Cr sanctioned
₹3.09 Cr spent (56%)
07
Constr of GP Bhawan
90 works
₹4.39 Cr sanctioned
₹2.32 Cr spent (53%)
08
Constr of Cement Concrete Roads
381 works
₹3.65 Cr sanctioned
₹2.22 Cr spent (61%)
09
Construction of Bund
40 works
₹3.50 Cr sanctioned
₹1.22 Cr spent (35%)
10
Constr of Aganwadi
40 works
₹3.20 Cr sanctioned
₹2.28 Cr spent (71%)