Monitor — Ongoing Works
Rollup last refreshed: 2026-10-27 07:04:11.86929
Works ongoing
13,599
Sanctioned (pure scheme)
₹90.75 Cr
Expenditure since inception
₹36.68 Cr
Balance cost (unspent)
₹54.07 Cr
Wage ₹36.30 Cr · Material ₹17.76 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
12,236 works
₹33.02 Cr sanctioned
₹14.06 Cr spent (43%)
02
Plantation
630 works
₹17.64 Cr sanctioned
₹6.15 Cr spent (35%)
03
Construction of Tank
52 works
₹8.54 Cr sanctioned
₹4.96 Cr spent (58%)
04
Construction of Well
229 works
₹7.44 Cr sanctioned
₹3.14 Cr spent (42%)
05
Construction of Road and Culvert
16 works
₹3.08 Cr sanctioned
₹1.45 Cr spent (47%)
06
Farm Pond
96 works
₹2.89 Cr sanctioned
₹89.75 L spent (31%)
07
Construction of Check Dam/Stop Dam
47 works
₹2.80 Cr sanctioned
₹1.36 Cr spent (49%)
08
Constr of GP Bhawan
9 works
₹2.44 Cr sanctioned
₹22.74 L spent (9%)
09
Construction of Percolation Tank
42 works
₹2.14 Cr sanctioned
₹68.87 L spent (32%)
10
Nursery Development
3 works
₹1.63 Cr sanctioned
₹12.46 L spent (8%)