Monitor — Ongoing Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
Reset filters
Works ongoing
41
Sanctioned (pure scheme)
₹70.65 L
Expenditure since inception
₹51.66 L
Balance cost (unspent)
₹18.99 L
Wage ₹10.96 L · Material ₹8.04 L
Expenditure trend
−₹20.03 L
This Week
−₹1.49 Cr
Last Week
▲ 86.6% vs last week
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹30.09 L
Mandays trend
-34,371
This Week
-94,475
Last Week
▲ 63.6%
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹22.70 L sanctioned
₹22.38 L spent (99%)
02
Plantation
9 works
₹17.66 L sanctioned
₹5.40 L spent (31%)
03
Construction of Well
4 works
₹11.69 L sanctioned
₹8.58 L spent (73%)
04
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.67 L spent (93%)
05
Rural Housing
20 works
₹4.68 L sanctioned
₹3.52 L spent (75%)
06
Construction of Percolation Tank
2 works
₹2.95 L sanctioned
₹2.30 L spent (78%)
07
Construction of Bund
1 works
₹1.81 L sanctioned
₹1.32 L spent (73%)
08
Construction of Tank
1 works
₹1.48 L sanctioned
₹1.16 L spent (79%)
09
Farm Pond
1 works
₹1.48 L sanctioned
₹1.13 L spent (77%)
10
Constr of Cement Concrete Roads
1 works
₹1.20 L sanctioned
₹1.19 L spent (100%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 20 4.68 3.52 1.16
75%
2 Plantation 9 17.66 5.40 12.27
31%
3 Construction of Well 4 11.69 8.58 3.11
73%
4 Construction of Percolation Tank 2 2.95 2.30 0.65
78%
5 Construction of Bund 1 1.81 1.32 0.49
73%
6 Construction of Road and Culvert 1 22.70 22.38 0.32
99%
7 Constr of Aganwadi 1 5.00 4.67 0.33
93%
8 Construction of Tank 1 1.48 1.16 0.31
79%
9 Farm Pond 1 1.48 1.13 0.34
77%
10 Constr of Cement Concrete Roads 1 1.20 1.19 0.00
100%
Total 41 70.65 51.66 18.99
All 10 rows (zero-value rows hidden) ⇩ Export to Excel