Monitor — Ongoing Works
Rollup last refreshed: 2026-09-08 06:51:44.520597
Works ongoing
16
Sanctioned (pure scheme)
₹64.68 L
Expenditure since inception
₹90,600
Balance cost (unspent)
₹63.77 L
Wage ₹38.96 L · Material ₹24.81 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
2 works
₹21.68 L sanctioned
₹0 spent (0%)
02
Construction of Check Dam/Stop Dam
2 works
₹21.56 L sanctioned
₹31,200 spent (1%)
03
Construction of Tank
1 works
₹9.67 L sanctioned
₹0 spent (0%)
04
Farm Pond
3 works
₹5.73 L sanctioned
₹3,900 spent (1%)
05
Construction of Percolation Tank
2 works
₹3.97 L sanctioned
₹50,100 spent (13%)
06
Rural Housing
5 works
₹1.35 L sanctioned
₹0 spent (0%)
07
Constr of Cement Concrete Roads
1 works
₹73,094 sanctioned
₹5,400 spent (7%)
08
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)