Monitor — Ongoing Works

Rollup last refreshed: 2026-09-06 07:04:10.165253
to
Reset filters
Works ongoing
24
Sanctioned (pure scheme)
₹36.63 L
Expenditure since inception
₹6.11 L
Balance cost (unspent)
₹30.51 L
Wage ₹13.74 L · Material ₹16.77 L
Expenditure trend
₹29.16 Cr
This Week
₹28.12 Cr
Last Week
▲ 3.7% vs last week
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹33.18 L
Mandays trend
12,34,730
This Week
9,10,292
Last Week
▲ 35.6%
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-16,630

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Recharge Pits
2 works
₹16.53 L sanctioned
₹2.42 L spent (15%)
02
Repair & maint of Pond/ Tank
2 works
₹4.47 L sanctioned
₹2,222 spent (0%)
03
Construction of Trench
2 works
₹3.66 L sanctioned
₹386 spent (0%)
04
Rural Housing
11 works
₹2.97 L sanctioned
₹1.17 L spent (39%)
05
Plantation
1 works
₹2.67 L sanctioned
₹261 spent (0%)
06
Construction of Percolation Tank
1 works
₹2.00 L sanctioned
₹1.67 L spent (84%)
07
Constr of Gabion
2 works
₹1.72 L sanctioned
₹26,906 spent (16%)
08
Farm Pond
1 works
₹1.48 L sanctioned
₹27,927 spent (19%)
09
Constr of Cement Concrete Roads
1 works
₹88,000 sanctioned
₹22,113 spent (25%)
10
Well Recharge
1 works
₹25,899 sanctioned
₹5,481 spent (21%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 11 2.97 1.17 1.80
39%
2 Construction of Recharge Pits 2 16.53 2.42 14.11
15%
3 Construction of Trench 2 3.66 0.00 3.66
0%
4 Constr of Gabion 2 1.72 0.27 1.45
16%
5 Repair & maint of Pond/ Tank 2 4.47 0.02 4.45
1%
6 Well Recharge 1 0.26 0.05 0.20
21%
7 Farm Pond 1 1.48 0.28 1.20
19%
8 Plantation 1 2.67 0.00 2.66
0%
9 Constr of Cement Concrete Roads 1 0.88 0.22 0.66
25%
10 Construction of Percolation Tank 1 2.00 1.67 0.33
84%
Total 24 36.63 6.11 30.51
All 10 rows (zero-value rows hidden) ⇩ Export to Excel