Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
11,666
Sanctioned (pure scheme)
₹203.94 Cr
Expenditure since inception
₹99.26 Cr
Balance cost (unspent)
₹104.68 Cr
Wage ₹57.09 Cr · Material ₹47.59 Cr
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Slowest spending this week — worth a look
- KHANDWA — PANDHANA−₹93.68 L
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,404 works
₹31.73 Cr sanctioned
₹7.66 Cr spent (24%)
02
Construction of Tank
296 works
₹27.29 Cr sanctioned
₹16.49 Cr spent (60%)
03
Construction of Road and Culvert
158 works
₹26.84 Cr sanctioned
₹20.11 Cr spent (75%)
04
Construction of Well
644 works
₹17.95 Cr sanctioned
₹7.43 Cr spent (41%)
05
Rural Housing
6,926 works
₹16.27 Cr sanctioned
₹10.05 Cr spent (62%)
06
Repair & maint of Pond/ Tank
177 works
₹13.90 Cr sanctioned
₹8.70 Cr spent (63%)
07
Construction of Percolation Tank
280 works
₹10.17 Cr sanctioned
₹4.48 Cr spent (44%)
08
Construction of Check Dam/Stop Dam
100 works
₹6.61 Cr sanctioned
₹3.08 Cr spent (47%)
09
Cattle Shed
144 works
₹6.26 Cr sanctioned
₹2.73 Cr spent (44%)
10
Farm Pond
348 works
₹5.88 Cr sanctioned
₹2.01 Cr spent (34%)