Works ongoing
10,074
Sanctioned (pure scheme)
₹160.50 Cr
Expenditure since inception
₹73.65 Cr
Balance cost (unspent)
₹86.84 Cr
Wage ₹48.48 Cr · Material ₹38.36 Cr
Expenditure trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Slowest spending this week — worth a look
Mandays trend
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,050 works
₹32.09 Cr sanctioned
₹12.13 Cr spent (38%)
02
Construction of Well
586 works
₹23.41 Cr sanctioned
₹12.08 Cr spent (52%)
03
Rural Housing
5,898 works
₹13.83 Cr sanctioned
₹9.39 Cr spent (68%)
04
Farm Pond
667 works
₹13.64 Cr sanctioned
₹5.21 Cr spent (38%)
05
Construction of Tank
92 works
₹11.99 Cr sanctioned
₹5.47 Cr spent (46%)
06
Construction of Check Dam/Stop Dam
265 works
₹9.75 Cr sanctioned
₹3.71 Cr spent (38%)
07
Construction of Bund
172 works
₹8.88 Cr sanctioned
₹3.93 Cr spent (44%)
08
Construction of Percolation Tank
147 works
₹6.73 Cr sanctioned
₹2.15 Cr spent (32%)
09
Construction of Road and Culvert
34 works
₹6.45 Cr sanctioned
₹5.17 Cr spent (80%)
10
Repair & maint of Pond/ Tank
60 works
₹4.89 Cr sanctioned
₹2.68 Cr spent (55%)