Monitor — Ongoing Works
Rollup last refreshed: 2026-09-08 06:51:44.520597
Works ongoing
13
Sanctioned (pure scheme)
₹54.88 L
Expenditure since inception
₹13,798
Balance cost (unspent)
₹54.74 L
Wage ₹17.45 L · Material ₹37.29 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹18.33 L sanctioned
₹13,798 spent (1%)
02
Construction of Road and Culvert
1 works
₹17.90 L sanctioned
₹0 spent (0%)
03
Plantation
1 works
₹6.78 L sanctioned
₹0 spent (0%)
04
Culvert
2 works
₹5.34 L sanctioned
₹0 spent (0%)
05
Constr of Cement Concrete Roads
3 works
₹2.83 L sanctioned
₹0 spent (0%)
06
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹0 spent (0%)
07
Solid and Liquid Waste Management
1 works
₹1.77 L sanctioned
₹0 spent (0%)
08
Constr of GP Bhawan
1 works
₹11,000 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
1 works
₹2,000 sanctioned
₹0 spent (0%)
10
Construction of Toilets
1 works
₹0 sanctioned
₹0 spent (0%)