Monitor — Ongoing Works
Rollup last refreshed: 2026-10-27 06:52:31.645166
Works ongoing
8
Sanctioned (pure scheme)
₹3.99 L
Expenditure since inception
₹1.27 L
Balance cost (unspent)
₹2.72 L
Wage ₹2.72 L · Material ₹0
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
1 works
₹2.10 L sanctioned
₹1.06 L spent (50%)
02
Rural Housing
7 works
₹1.89 L sanctioned
₹21,300 spent (11%)
03
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
04
Terracing
0 works
₹0 sanctioned
₹0 spent (0%)
05
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
06
Works for Flood Control and Protection
0 works
₹0 sanctioned
₹0 spent (0%)