Works ongoing
33
Sanctioned (pure scheme)
₹10.67 L
Expenditure since inception
₹5.90 L
Balance cost (unspent)
₹4.77 L
Wage ₹4.14 L · Material ₹63,000
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
- VIDISHA — LATERI−₹52.78 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
31 works
₹8.37 L sanctioned
₹4.65 L spent (56%)
02
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.17 L spent (65%)
03
Solid and Liquid Waste Management
1 works
₹50,000 sanctioned
₹6,948 spent (14%)
04
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
05
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)