Monitor — Ongoing Works
Rollup last refreshed: 2026-10-17 07:04:51.670761
Works ongoing
4,534
Sanctioned (pure scheme)
₹89.93 Cr
Expenditure since inception
₹34.34 Cr
Balance cost (unspent)
₹55.58 Cr
Wage ₹34.43 Cr · Material ₹21.15 Cr
Expenditure trend
Jun-26
Jul-26
Aug-26
Sep-26
Oct-26
Slowest spending this month — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
747 works
₹21.80 Cr sanctioned
₹6.73 Cr spent (31%)
02
Farm Pond
452 works
₹11.94 Cr sanctioned
₹1.23 Cr spent (10%)
03
Constr of Cement Concrete Roads
71 works
₹8.83 Cr sanctioned
₹6.74 Cr spent (76%)
04
Construction of Check Dam/Stop Dam
154 works
₹8.82 Cr sanctioned
₹4.74 Cr spent (54%)
05
Construction of Tank
70 works
₹6.73 Cr sanctioned
₹2.70 Cr spent (40%)
06
Rural Housing
2,056 works
₹5.86 Cr sanctioned
₹1.83 Cr spent (31%)
07
Construction of Road and Culvert
27 works
₹5.82 Cr sanctioned
₹3.83 Cr spent (66%)
08
Cattle Shed
292 works
₹5.48 Cr sanctioned
₹2.67 Cr spent (49%)
09
Construction of Trench
134 works
₹4.09 Cr sanctioned
₹1.37 Cr spent (34%)
10
Construction of Well
97 works
₹2.79 Cr sanctioned
₹98.45 L spent (35%)