Monitor — Ongoing Works
Rollup last refreshed: 2026-08-18 08:29:42.702774
Works ongoing
6,015
Sanctioned (pure scheme)
₹79.99 Cr
Expenditure since inception
₹36.09 Cr
Balance cost (unspent)
₹43.90 Cr
Wage ₹27.64 Cr · Material ₹16.26 Cr
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
707 works
₹20.91 Cr sanctioned
₹5.90 Cr spent (28%)
02
Rural Housing
4,356 works
₹10.48 Cr sanctioned
₹5.76 Cr spent (55%)
03
Farm Pond
336 works
₹8.90 Cr sanctioned
₹1.22 Cr spent (14%)
04
Constr of Cement Concrete Roads
62 works
₹8.75 Cr sanctioned
₹6.73 Cr spent (77%)
05
Construction of Check Dam/Stop Dam
57 works
₹7.49 Cr sanctioned
₹4.54 Cr spent (61%)
06
Construction of Road and Culvert
26 works
₹5.81 Cr sanctioned
₹3.81 Cr spent (66%)
07
Construction of Tank
40 works
₹5.04 Cr sanctioned
₹2.57 Cr spent (51%)
08
Cattle Shed
100 works
₹3.64 Cr sanctioned
₹2.59 Cr spent (71%)
09
Construction of Well
87 works
₹2.51 Cr sanctioned
₹94.66 L spent (38%)
10
Construction of Trench
24 works
₹1.38 Cr sanctioned
₹66.66 L spent (48%)