Monitor — Ongoing Works

Rollup last refreshed: 2026-10-04 06:52:14.898992
to
Reset filters
Works ongoing
4,538
Sanctioned (pure scheme)
₹89.60 Cr
Expenditure since inception
₹2.47 Cr
Balance cost (unspent)
₹87.13 Cr
Wage ₹45.87 Cr · Material ₹41.26 Cr
Expenditure trend
₹28.71 Cr
This Week
₹23.43 Cr
Last Week
▲ 22.5% vs last week
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
  • DAMOH — PATERA−₹4.99 L
Mandays trend
11,37,836
This Week
11,32,881
Last Week
▲ 0.4%
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
  • MORENA — AMBAH6

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
746 works
₹21.80 Cr sanctioned
₹1.10 Cr spent (5%)
02
Farm Pond
447 works
₹11.80 Cr sanctioned
₹2.14 L spent (0%)
03
Constr of Cement Concrete Roads
71 works
₹8.83 Cr sanctioned
₹89,087 spent (0%)
04
Construction of Check Dam/Stop Dam
153 works
₹8.82 Cr sanctioned
₹13.26 L spent (2%)
05
Construction of Tank
67 works
₹6.64 Cr sanctioned
₹8.74 L spent (1%)
06
Rural Housing
2,093 works
₹5.97 Cr sanctioned
₹39.70 L spent (7%)
07
Construction of Road and Culvert
27 works
₹5.82 Cr sanctioned
₹1.17 L spent (0%)
08
Cattle Shed
283 works
₹5.39 Cr sanctioned
₹6.84 L spent (1%)
09
Construction of Trench
133 works
₹4.04 Cr sanctioned
₹47.12 L spent (12%)
10
Construction of Well
97 works
₹2.79 Cr sanctioned
₹2.94 L spent (1%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 2,093 5.97 0.40 5.57
7%
2 Plantation 746 21.80 1.10 20.70
5%
3 Farm Pond 447 11.80 0.02 11.78
0%
4 Cattle Shed 283 5.39 0.07 5.32
1%
5 Construction of Check Dam/Stop Dam 153 8.82 0.13 8.68
2%
6 Construction of Trench 133 4.04 0.47 3.57
12%
7 Construction of Well 97 2.79 0.03 2.76
1%
8 Constr of Cement Concrete Roads 71 8.83 0.01 8.82
0%
9 Construction of Tank 67 6.64 0.09 6.55
1%
10 Roof Water Harvesting on gov/panchayat bldg 53 0.77 0.08 0.69
11%
11 Well Recharge 46 0.52 0.01 0.51
1%
12 Construction of Bund 42 1.27 0.00 1.27
0%
13 Construction of NADEP/Vermi Compost Pit 37 0.07 0.00 0.07
2%
14 Solid and Liquid Waste Management 33 0.22 0.00 0.22
1%
15 Construction of Recharge Pits 31 0.23 0.03 0.20
13%
16 Construction of Road and Culvert 27 5.82 0.01 5.81
0%
17 Land Development 25 0.43 0.00 0.43
0%
18 Repair & maint of Pond/ Tank 18 0.68 0.00 0.68
0%
19 Construction of Percolation Tank 16 0.53 0.00 0.53
0%
20 Goat Shelter 13 0.09 0.00 0.09
0%
21 Repair & Maint of Check Dam/Stop Dam 12 0.26 0.00 0.26
0%
22 Constr of Aganwadi 11 0.36 0.00 0.36
0%
23 Other Works 10 0.12 0.00 0.12
3%
24 Community Sanitary Complex 8 0.21 0.00 0.21
1%
25 Constr of Compound wall 6 0.11 0.00 0.11
0%
26 Boulder Check/Gully Plug 6 0.08 0.00 0.08
5%
27 Constr of GP Bhawan 5 0.37 0.00 0.36
1%
28 Construction of Embankment 5 0.22 0.00 0.22
0%
29 (uncategorised) 4 0.01 0.00 0.01
7%
30 Constr of Gabion 4 0.17 0.00 0.17
0%
31 Poultry Shelter 4 0.02 0.00 0.02
2%
32 Repair & maint of Road 3 0.04 0.00 0.04
0%
33 Repair & maint of Water Harvesting Structures 3 0.14 0.00 0.14
0%
34 Repair & maint of Percolation Tank 3 0.07 0.00 0.07
0%
35 Nursery Development 2 0.12 0.00 0.12
2%
36 Terracing 2 0.03 0.00 0.03
0%
37 Construction of Toilets 2 0.01 0.00 0.01
0%
38 Construction of Crematorium 2 0.02 0.00 0.02
0%
39 Construction of Fish Drying Infrastructure 2 0.08 0.00 0.08
0%
40 Underground Dyke for Ground Water Recharge 2 0.07 0.00 0.07
0%
41 Repair & Maint of Fish Drying Infrastructure 2 0.09 0.00 0.09
0%
42 Repair & Maint of Community infrastructure 2 0.05 0.00 0.05
0%
43 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.01 0.00 0.01
0%
44 Construction of Spur 1 0.02 0.00 0.02
0%
45 Construction of Village Haats 1 0.01 0.00 0.01
0%
46 Works for Flood Control and Protection 1 0.08 0.00 0.07
3%
47 Piggery Shelter 1 0.08 0.00 0.08
0%
48 Construction of Play field 1 0.04 0.00 0.04
0%
49 Renovation of Canal 1 0.02 0.00 0.02
0%
Total 4,538 89.60 2.47 87.13
All 49 rows (zero-value rows hidden) ⇩ Export to Excel