Monitor — Ongoing Works
Rollup last refreshed: 2026-10-27 06:52:31.645166
Works ongoing
12,902
Sanctioned (pure scheme)
₹147.71 Cr
Expenditure since inception
₹10.13 Cr
Balance cost (unspent)
₹137.58 Cr
Wage ₹81.26 Cr · Material ₹56.32 Cr
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
2,403 works
₹61.52 Cr sanctioned
₹2.74 Cr spent (4%)
02
Rural Housing
9,222 works
₹24.90 Cr sanctioned
₹6.18 Cr spent (25%)
03
Construction of Well
528 works
₹16.73 Cr sanctioned
₹22.55 L spent (1%)
04
Construction of Tank
109 works
₹13.29 Cr sanctioned
₹70.51 L spent (5%)
05
Construction of Road and Culvert
47 works
₹9.08 Cr sanctioned
₹15.23 L spent (2%)
06
Farm Pond
174 works
₹4.69 Cr sanctioned
₹3.79 L spent (1%)
07
Construction of Percolation Tank
57 works
₹2.52 Cr sanctioned
₹2.65 L spent (1%)
08
Well Recharge
69 works
₹2.30 Cr sanctioned
₹2.10 L spent (1%)
09
Constr of GP Bhawan
19 works
₹1.92 Cr sanctioned
₹7,200 spent (0%)
10
Construction of Check Dam/Stop Dam
16 works
₹1.49 Cr sanctioned
₹1.15 L spent (1%)