Monitor — Ongoing Works
Rollup last refreshed: 2026-09-15 07:04:12.299416
Works ongoing
10,653
Sanctioned (pure scheme)
₹164.21 Cr
Expenditure since inception
₹62.76 Cr
Balance cost (unspent)
₹101.45 Cr
Wage ₹61.06 Cr · Material ₹40.39 Cr
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
- RAJGARH — SARANGPUR−₹97.29 L
Mandays trend
Jun-26
Jul-26
Aug-26
Sep-26
Lowest mandays this month — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
1,643 works
₹76.41 Cr sanctioned
₹27.19 Cr spent (36%)
02
Construction of Well
688 works
₹21.82 Cr sanctioned
₹9.98 Cr spent (46%)
03
Rural Housing
7,270 works
₹19.63 Cr sanctioned
₹8.78 Cr spent (45%)
04
Farm Pond
305 works
₹10.81 Cr sanctioned
₹2.63 Cr spent (24%)
05
Construction of Tank
66 works
₹7.67 Cr sanctioned
₹2.86 Cr spent (37%)
06
Construction of Road and Culvert
61 works
₹6.68 Cr sanctioned
₹3.91 Cr spent (59%)
07
Construction of Percolation Tank
56 works
₹2.76 Cr sanctioned
₹40.97 L spent (15%)
08
Cattle Shed
61 works
₹2.20 Cr sanctioned
₹1.85 Cr spent (84%)
09
Constr of GP Bhawan
24 works
₹2.17 Cr sanctioned
₹1.56 Cr spent (72%)
10
Construction of Trench
32 works
₹2.01 Cr sanctioned
₹23.91 L spent (12%)